First Quantum Mineral ordered to stop its operation

1st December 2023 First Quantum Mineral ordered to stop its operation

Panama’s Supreme Court

After Panama’s Supreme Court of Justice has ruled that the mining contract for the Cobre Panama copper mine is unconstitutional the First Quantum Minerals has been asked by Panama to stop their operation. The decision of the Supreme Court has ended the six weeks of protests against the First Quantum Minerals contract which was at first triggered by the government’s renewal of its contract with the company. Among others protesters blocked the Pan-American highway and other key roads, causing fuel and food shortages in some regions. The contract which was at first renewed has given the company the right for 20 years of mining operation with an option to extend the rights for the next 20 years in return for a $375 million annual revenue fee.

Transition has started

Panama’s President Laurentino Cortizo Cohen has stated that he would “abide by the decision of the Supreme Court”. He has further added that “the transition process for the orderly and safe closure of the mine” has started.

Concerns

Minera Panama, First Quantum Minerals’s local unit has announced that concerning the ruling of the Supreme Court of Justice, it reiterates that transparency and compliance with the laws have always been fundamental for the development of its operations and reiterates the interest in promoting dialogue to find solutions. Moreover, the company believes some key questions need to be answered among others how does the Government plan to prevent the arrival of illegal miners, what are the plans of the Ministry of Labor for the support, training, and continuous development of the 40,000 people employed directly and indirectly by Cobre Panamá in the future.

Cobre Panama

The company has indicated that Cobre Panama has more than 7,000 direct employees and 33,000 contractors and suppliers which will be affected by this decision.

First Quantum announced that it would comment further once it studied the details of the ruling.

Cobre Panama copper mine began producing copper in 2019. It was providing around 1% of the global copper output. According to government data, the copper operation in Cobre Panama accounted for 3.5% of Panama’s GDP in 2021.

Next WMC Congress

World Mining Congress

2028

The 28th World Mining Congress will be organized in China. Detailed information will be provided in future.

Learn more
28th
Next IOC Meeting

IOC / WMC Meeting

2027

The 108th IOC/WMC meeting will be organized in Kosice, Slovakia.

Learn more
108th

Our news Others news

11th September 2026 Forge resources completes La Estrella underground ramp

Ancient mine tunnel illuminated by warm lights. Source: Photo by Yosuke Ota on Unsplash

Forge Resources Corp. has informed that the Company has reached an important underground development milestone at…

7th September 2026 Greenland Mines completes Sarfartoq acquisition, strengthening western NdPr supply potential

Minerals collection. Source: Photo by Tasha Kostyuk on Unsplash

Greenland Mines Ltd. has completed the acquisition of the Sarfartoq Nd-Pr Rare Earths Project in southwest…

1st September 2026 China’s reported 30 million tonne uranium discovery could reshape the global nuclear supply chain

The nuclear power plant at night. Source: Photo by Nicolas HIPPERT on Unsplash

A reported uranium discovery beneath China’s Ordos Desert in Inner Mongolia is drawing attention far beyond…

26th August 2026 Taco Lubbock secures ASME and National Board Certifications

Macro view of lit sparkler throwing sparks in all directions. Source: Unsplash.

For industrial manufacturers, certification is more than a compliance milestone. It is a measure of whether…

20th August 2026 Lundin Mining revises Caserones 2026 guidance

Open-pit mine top-view. Source: Photo by omid roshan on Unsplash

Extreme weather is becoming an increasingly material operational risk for the global mining industry. In northern…

17th August 2026 Blue Moon Metals pushes back on short-seller claims as Nussir advances toward 2027 production

Minerals collection. Source: Photo by Tasha Kostyuk on Unsplash

Blue Moon Metals has issued a detailed response to a short-seller report from Viceroy Research Group…

11th August 2026 Barrick and Newmont reset Nevada gold mines partnership

Open pit mine. Source: Photo by omid roshan on Unsplash

Two of the world’s largest gold miners have reached an agreement that could reshape both the…

5th August 2026 Codelco pauses Andes Norte to better understand deep-seated seismic risk

Mining helmets in changing room. Source:Photo by Pop & Zebra on Unsplash

Codelco has announced the temporary suspension of development and construction activities at the Andes Norte Project…

3rd August 2026 SAGA Metals and Temas advance North American vanadium processing

Open peat mine aerial view. Source: ivan-bandura Unsplashed

As governments and manufacturers race to secure resilient critical mineral supply chains, exploration success alone is…

29th July 2026 Scotia Metals emerges with a 1,200 km² lithium platform in Nova Scotia

Stocks chart. Source: Photo by Maxim Hopman on Unsplash

Scotia Metals Corp. has completed a business combination that transforms the former Cross River Ventures into…